== Attendees ==

 

Chair: Chris Shepherd

Community Rep: Ian Jackson

 

AMD: Aravind Gopalakrishnan

Citrix: Lars Kurth

Intel: Donald D Dugger

Oracle: Marcos Matsunaga

Verizon: Don Slutz (Lead)

 

IMPORTANT REMINDER: Chris will set up new meeting invite with new dial in details and Lars will cancel the old one

 

== Actions ==

All closed

 

== Agenda ==

 

=== Discuss Don's Quote ===

Earthlink : Fully fledged data centre (see previous mail)

Cost breakdown:

- Setup: $935.00

- Monthly: $825.00

- Includes Internet

- There is also an additional charge of 19 cents per kWh (needs to be confirmed)

 

Unclear: Taxes

 

Don is also talking to a small consultancy re Allnet computer solutions (4-5 official employees). No hourly rate yet.

 

Lacking: Sysadmin (to be provided by Allnet computer solutions)

Lacking: Backup (assuming Allnet computer solutions would do backup)

 

Don Dugger: what backup do we need?

Ian J: Most of the machines will not need backups, but we probably only need "control plane machines/VM" and "machines which keep logs and configs" to be backed up. Maybe only need to backup 2-3 physical hosts

 

[Action] DonS to confirm power cost and taxes

[Action] Ian to speak to Allnet about requirements after an e-mail introduction  by DonS

 

=== Ian's Proposal (http/www.jump.net.uk/) ===

Small company (1-2 employees, Ian knows proprietor personally) which provides hosting consulting services. They are a re-seller of Telehouse (http://www.telehouse.net/) and provide support / consultancy

 

Quote structured differently to Don's : Jump only charge for power consumption (

According to Ian’s initial calculations we are looking at GBP 1-2L per host per year

To get bill size we need to estimate power consumption – aka establish a power budget

 

Also do consultancy / sysadmin support : GBP 50 per hour

* Steady state a few hours per week

* Set-up a week or two week's work

Also do have back-up facilities

 

Jump prices may be higher that the budget

 

[Action] Ian and Chris cost put together power budget based on original mail from Ian

[Action] Ian spec out detailed proposal (based on 24 servers and power budget)

[Action] Don spec out detailed proposal (based on 24 servers and power budget)

 

Costing basis:

* 4h per week continuously for consultancy /sysadmin

* 100h for set-up

 

=== Budget ===

We do have the following line-items in the budget:

* COLO cost per quarter: USD 12K (USD 4K or GBP 2.38K per month)

Remote admin and support of environment: USD 11.25K (3.75K or GBPO 2.23K per month). 

 

=== Hardware ===

In previous conversations, the Linux Foundation indicated that it would get heavy discounts on hardware.

 

[Action] Lars to follow up with LF on finding out HW discounts. CC list (to happen in parallel with power budget)

_______________________________________________
Wg-test-framework mailing list
Wg-test-framework@xxxxxxxxxxxxxxxxxxxx
http://lists.xenproject.org/cgi-bin/mailman/listinfo/wg-test-framework

 


Rackspace

Lists.xenproject.org is hosted with RackSpace, monitoring our
servers 24x7x365 and backed by RackSpace's Fanatical Support®.