[Wg-test-framework] Overview of Support Hour Infrastructure Spending of the Project



Hi all, 
Below you see the current usage of hours including spending for infrastructure work. At current projections, we will have 62 hours left at the end of the year. In any case, we will have plenty of hours for the Test Lab expansion (in particular as Feb & March & April contained 50%+ of such work).
Regards
Lars

Start End Days Hours Avg H / Month Remaining / Carry Over to date Estimate: Remaining after run-rate
Contract 1 / 15-16 01/11/2015 31/8/2016 38 304 28 23
Contract 2 / 16 1/9/2016 31/12/2016 5 37 9 292
Contract 2 / 17 1/11/2016 36 292 19 215 62
2016 Contract 1 Contract 2
Hours Nov / Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Total per Month 26 36 40 33 23 23 23 59 18 10 16 9 3
2017 Contract 2
Hours N/A Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Total per Month 4 18 21 33
_______________________________________________
Wg-test-framework mailing list
Wg-test-framework@xxxxxxxxxxxxxxxxxxxx
https://lists.xenproject.org/cgi-bin/mailman/listinfo/wg-test-framework

 


Rackspace

Lists.xenproject.org is hosted with RackSpace, monitoring our
servers 24x7x365 and backed by RackSpace's Fanatical Support®.