Ian, 

As far as server ETA goes, we are looking at 10 to 12 working days for the
Main Servers then a few days for the supplier to assemble and smoke test
them.  I think we are looking at the week of the 24th before we get the
first servers.  Gigabit has a 6 week lead time. I am assuming that we will
see the PDU's and the switches before we get the rest of the hardware.

Paul

-----Original Message-----
From: Ian Jackson [mailto:Ian.Jackson@xxxxxxxxxxxxx] 
Sent: Tuesday, November 11, 2014 6:31 AM
To: Paul L. George
Cc: wg-test-framework@xxxxxxxxxxxxxxxxxxxx
Subject: RE: [Wg-test-framework] Network Di8agram

Paul L. George writes ("RE: [Wg-test-framework] Network Di8agram"):
> I will try to get a preliminary  project plan together for Wednesday.

Thanks.

> Making specific plans at this point is premature.  I cannot schedule 
> people until I have equipment or definite ETA's in hand.

I assume your suppliers have given you delivery estimates ?

> I know the equipment has been ordered from the manufactures but I do 
> not have and ETA yet.

I don't understand.  Can you not get an ETA ?

> You mentioned setting up VLANS.  I need to know more because I am 
> assuming that the switches and the PDU's have  be setup pretty early in he
process.

Please see my file plumbing.txt to which I've provided links several times.
Here it is again:

http://xenbits.xen.org/gitweb/?p=people/iwj/colo-for-testing.git;a=blob;f=pl
umbing.txt;hb=HEAD

Thanks,
Ian.


_______________________________________________
Wg-test-framework mailing list
Wg-test-framework@xxxxxxxxxxxxxxxxxxxx
http://lists.xenproject.org/cgi-bin/mailman/listinfo/wg-test-framework


 


Rackspace

Lists.xenproject.org is hosted with RackSpace, monitoring our
servers 24x7x365 and backed by RackSpace's Fanatical Support®.